Almost every feasibility study ends on reassuring numbers: a positive NPV, an internal rate of return (IRR) above the required return, a reasonable payback period. All of those numbers rest on a single base case, one set of assumptions about price, volume, costs, the exchange rate and timing. Sensitivity analysis in a feasibility study is the chapter that tests those assumptions one by one and tells you which of them actually carry the project and which hardly matter. If you are a foreign company sizing up the Egyptian market, an Egyptian abroad thinking of putting savings to work at home, or an investor in Egypt weighing a project against Egyptian bank savings certificates, this chapter is what separates a study you read from a study you can decide on.
This guide sets out the method as international project-appraisal manuals describe it: choosing the variables, identifying the critical ones, calculating switching values, and moving on to scenarios and then to probabilistic analysis. It then applies each step to a fully worked, illustrative example of a cold-storage warehouse in an Egyptian industrial zone, and closes with common mistakes and a checklist for your own study.
The base case is your best estimate for each variable taken on its own. It is not a promise. A project showing an NPV of EGP 70 million in the base case could be robust enough to absorb large forecasting errors, or fragile enough that a small error in one assumption pushes it below the required return. The headline figure cannot tell the two apart, which is why serious investors, banks and development lenders expect it to come with a sensitivity and risk analysis.
Two features of the Egyptian market make this chapter matter more. First, some variables have recently moved in jumps rather than steps. On 6 March 2024 the Central Bank of Egypt (CBE), the country's central bank and monetary authority, raised interest rates by 600 basis points and let the market set the exchange rate; the pound weakened to 50.70 per dollar that day before settling at about 49.601. Second, an investor coming from abroad measures results in another currency and compares them with opportunities elsewhere, so the margin of safety matters as much as the base-case figure.
What is sensitivity analysis in a feasibility study?
The European Commission's guide to cost-benefit analysis of investment projects describes sensitivity analysis as the tool that identifies a project's critical variables: those whose variations, up or down, have the largest impact on its financial or economic performance2. The analysis is carried out by varying one variable at a time and measuring the effect of that change on NPV2. An open university textbook on financial management puts it more simply: sensitivity analysis is the most basic form of risk analysis, looking at how a single input variable affects NPV3.
Three tools build on it, in rising order of complexity:
- Switching value: the value a variable would have to take for the project's NPV to become zero or, more generally, for the outcome to fall below the minimum acceptable level2. The Asian Development Bank (ADB) asks for switching values to be presented for key variables, showing the change needed for the decision to flip from acceptance to rejection4.
- Scenario analysis: studies the impact of combinations of values taken by the critical variables, for example pairing optimistic or pessimistic values to build different realistic scenarios2. Unlike sensitivity analysis, a scenario changes several inputs at the same time3.
- Probabilistic analysis: assigns a probability distribution to each critical variable; the European Commission guide suggests the Monte Carlo method for this2. The ADB recommends a quantitative risk analysis for large projects and for those close to the cut-off rate4.
Sensitivity analysis does not forecast. It will not tell you what the exchange rate or occupancy will be. It tells you which of those numbers deserves your time and money to verify before you commit, and where a reasonable estimate is good enough. It also assumes you have already calculated NPV and IRR; if not, start with our guide to NPV and IRR.
Which variables to test for a project in Egypt
The list varies by sector, but seven groups recur in most investment projects in Egypt.
Price and volume
Selling price and sales volume, or capacity utilisation, are usually the two most powerful variables in any study, because revenue moves with them in full while most fixed costs stay where they are. Volume includes the speed of ramp-up: a project that reaches 80% of capacity in year three is very different from one that gets there in year five.
Construction cost and delay
Initial investment and construction time are among the most optimistic assumptions in studies worldwide. A study published in 2003 covering 258 transport projects in 20 countries found that cost escalation is the rule rather than the exception, averaging 45% for rail, 34% for tunnels and bridges and 20% for roads5. Your project is not a railway or a road, but the lesson applies to any build: test a cost overrun and a late opening rather than adding a 5% contingency and moving on.
Exchange rate
The exchange rate affects the price of imported equipment at purchase, any operating costs linked to the dollar, and the value of your return if you measure it in foreign currency. On 25 November 2026 the CBE dollar rate opened at EGP 54.17 buying and EGP 54.30 selling6. We cover this variable in depth in our guide to measuring exchange rate risk on your dollar return; here it is one variable among several.
Energy prices
For electricity-intensive businesses such as cold chain, manufacturing and data centres, power can be the second-largest cost line. Egypt announced an increase in commercial electricity prices across all brackets averaging about 20% from April 20267. That does not mean the same increase will recur, but it gives a realistic range to test. Check which tariff class your project actually falls under (commercial or industrial, low or medium voltage), because increases are not uniform across classes.
Inflation and your ability to pass it on
Annual urban inflation in Egypt was 12.7% in October 2026, down from 13.9% in September, according to data from CAPMAS, the national statistics agency8. The issue is not the level of inflation as such but the gap between how fast your costs rise and how fast your prices can follow. Always test a case where your prices grow one or two percentage points a year slower than your costs.
Discount rate
The discount rate is the return you require for the risk you take, and in Egypt it is tied directly to interest rates. The CBE raised its key rates by 100 basis points on 29 October 2026, taking the overnight deposit rate to 20% and the lending rate to 21%8. But that is a short-term rate for banks and may change a great deal over your project's life. A sounder approach is to build the discount rate from the yield on a long-dated Egyptian government pound instrument on the study date plus a premium for project risk, and then test it like any other assumption.
Exit value
An investor who plans to sell after five or eight years assumes a sale value at the end of the period, and that value often supplies most of the NPV without anyone noticing. Test it as a separate variable, and also show the result without it.
Sensitivity analysis step by step
Step 1: break compound variables into their parts
The European Commission guide requires the variables tested to be independent of each other and as disaggregated as possible; its example is that revenue is a compound variable depending on two independent items, quantity and tariff2. Testing correlated variables distorts the results and double-counts the same effect2. Do not test revenue and price as two separate variables, or equipment cost and the exchange rate as two independent risks when one determines the other.
Step 2: find the critical variables with a 1% test
The same guide recommends treating a variable as critical when a change of plus or minus 1% from its base-case value changes NPV by more than 1%2. The test turns a ranking based on impressions into a number: a variable that moves NPV 9% for every 1% is far more dangerous than one that moves it 1.2%.
Step 3: test a uniform percentage and draw a tornado table
Next, move each variable by the same percentage, say 10% up and down, and rank them from largest effect to smallest. The result is usually called a tornado chart, because the long bars sit at the top and the short ones at the bottom. A common percentage makes comparison easy, but remember that a 10% move in price is not as likely as a 10% move in the exchange rate.
Step 4: calculate switching values
For each critical variable, find the value at which NPV falls to zero. Switching values are easier to discuss than percentages: "the project misses its required return if stabilised occupancy falls below 71%" sends you straight to the market to ask what occupancy competitors actually achieve.
Step 5: build scenarios
Combine the pessimistic values of the critical variables into one scenario and the optimistic ones into another. According to the European Commission guide, if NPV stays positive even in the pessimistic scenario, the project's risk can be assessed as low2.
Step 6: move to probabilistic analysis where needed
If the project is large or close to the cut-off, give each critical variable a probability distribution and run a Monte Carlo simulation. The European guide notes that in its simplest design, such as a triangular distribution, this step is always feasible2; a triangular distribution needs only three values: the minimum, the most likely and the maximum.
Illustrative example: a cold-storage warehouse in an Egyptian industrial zone
Illustrative example: all inputs are assumed for the explanation, all results were calculated in code and copied from its output, and amounts are in EGP millions rounded to two decimals. An Egyptian investor based in the Gulf and a foreign partner are studying a chilled and frozen storage warehouse with 15,000 pallet positions (the pallet being the usual unit of storage and pricing in warehousing) on leased land in an industrial zone near Cairo, serving food exporters and retail chains and charging in Egyptian pounds. The partners fund the project entirely with equity.
Inputs
- Investment: imported refrigeration equipment and racking worth USD 3.0 million, or EGP 162.90 million at EGP 54.30 per dollar, the CBE selling rate on the morning of 25 November 20266, plus EGP 140 million of local construction and fit-out. The total of EGP 302.90 million is depreciated on a straight line over 8 years (EGP 37.86 million a year). Opening working capital adds EGP 15 million, held constant for simplicity, so the year-zero outlay is EGP 317.90 million, about USD 5.85 million at the same rate.
- Occupancy: 55% in year one, 70% in year two and 80% from year three to year eight.
- Storage price: EGP 1,150 per pallet per month in year one, rising 10% a year, deliberately slower than current inflation and cost growth. Handling, sorting and packing services add revenue equal to 25% of storage revenue.
- Variable costs (handling labour and packaging) at 15% of revenue. Electricity at EGP 42 million in year one, rising 12% a year. Other fixed costs (land rent, management pay, maintenance, insurance) at EGP 32 million, rising 11% a year.
- Corporate income tax at 22.5% of net taxable profit9, with losses carried forward for simplicity.
- Exit at the end of year eight: a sale at four times that year's earnings before interest, tax, depreciation and amortisation (EBITDA), taxed at 22.5% on the full amount because the assets are fully depreciated in the books, plus recovery of the opening working capital. This is a simplification, as is the single depreciation life; the actual tax treatment of a share or asset sale, and tax depreciation lives, need a tax adviser.
- Discount rate: 26% in pounds, an illustrative figure equal to the CBE overnight deposit rate of 20%8 plus 6 percentage points. Many investors would ask for more on an all-equity greenfield project, which is why the discount rate is one of the variables we test.
Year one, step by step
- Storage revenue = 15,000 × 55% × EGP 1,150 × 12 months = EGP 113.85 million; services revenue = 113.85 × 25% = EGP 28.46 million. Total revenue EGP 142.31 million.
- Variable costs = 142.31 × 15% = EGP 21.35 million; electricity EGP 42.00 million; fixed costs EGP 32.00 million.
- EBITDA = 142.31 − 21.35 − 42.00 − 32.00 = EGP 46.97 million.
- Operating profit after depreciation = 46.97 − 37.86 = EGP 9.10 million; tax = 9.10 × 22.5% = EGP 2.05 million.
- Free cash flow = 46.97 − 2.05 = EGP 44.92 million.
Base-case results
| Year | Occupancy | Revenue | EBITDA | Free cash flow |
|---|---|---|---|---|
| 1 | 55% | 142.31 | 46.97 | 44.92 |
| 2 | 70% | 199.24 | 86.79 | 75.78 |
| 3 | 80% | 250.47 | 120.79 | 102.13 |
| 4 | 80% | 275.52 | 131.42 | 110.37 |
| 5 | 80% | 303.07 | 142.94 | 119.30 |
| 6 | 80% | 333.38 | 155.43 | 128.98 |
| 7 | 80% | 366.71 | 168.95 | 139.46 |
| 8 | 80% | 403.38 | 183.59 | 150.80 |
Exit value at the end of year eight = 4 × 183.59 = EGP 734.36 million; after 22.5% tax and the return of working capital, EGP 584.13 million remains. At 26%, NPV is EGP 73.47 million and IRR is 31.49%. On paper, the project passes.
One detail matters before any test. The present value of the after-tax exit value alone is EGP 89.59 million, while the present value of the eight years of operating cash flow plus the working-capital recovery falls EGP 16.12 million short of the investment. In other words, all of the NPV, and more, comes from assuming you can sell the business for four times its earnings after eight years. Breaking the result down reveals this first, and we come back to it below.
One variable at a time: the tornado table
We moved each variable 10% up and down with everything else held constant, and also measured the elasticity of NPV, meaning the percentage change in NPV for a 1% change in the variable:
| Variable | NPV at −10% | NPV at +10% | Change in NPV per 1% |
|---|---|---|---|
| Storage price (or occupancy) | 4.72 | 142.11 | 9.34% |
| Discount rate | 117.13 | 35.88 | −5.50% |
| Electricity cost | 92.19 | 54.75 | −2.55% |
| Exchange rate at equipment purchase (or its dollar price) | 88.28 | 58.67 | −2.02% |
| Other fixed costs | 87.25 | 59.69 | −1.88% |
| Local construction cost | 86.19 | 60.75 | −1.73% |
| Variable cost ratio | 85.58 | 61.36 | −1.65% |
| Exit multiple | 64.51 | 82.43 | 1.22% |
Three readings:
- Price and occupancy lead by a wide margin. A 10% fall in either takes NPV from 73.47 to 4.72, erasing 93.6% of it. They have the same effect in this model because revenue is their product; the difference between them lies in likelihood, not impact. Early-year occupancy is harder to estimate than price when competitors' rates are known.
- Every variable is critical by the 1% rule. Each one moves NPV by more than 1% for every 1% change. That is not a flaw in the rule; it signals that NPV is small relative to the cash flows, only EGP 73.47 million on an outlay of EGP 317.90 million. The thinner the margin, the more everything becomes critical, and the ranking then matters more than the label.
- The discount rate comes second. Moving it from 23.4% to 28.6% shifts NPV from 117.13 to 35.88. The discount rate is the investor's choice rather than a project variable, but we show it because a study should explain how it was chosen rather than state it as a given.
Switching values: how much can the project absorb?
Switching values turn the question round: instead of "what happens if the variable moves 10%?", you ask "how far must it move before NPV reaches zero?". We calculated them for each variable, holding the others constant:
| Variable | Change that sets NPV to zero | Value at the switch |
|---|---|---|
| Storage price | −10.68% | EGP 1,027 per pallet per month in year one instead of 1,150 |
| Occupancy | −10.68% | 71.45% once stabilised instead of 80% (49.12% in year one) |
| Discount rate | +21.12% | 31.49%, which is the IRR itself |
| Electricity cost | +39.10% | EGP 58.42 million in year one instead of 42 |
| Exchange rate at equipment purchase | +49.60% | EGP 81.23 per dollar instead of 54.30 |
| Other fixed costs | +53.11% | EGP 49.00 million in year one instead of 32 |
| Local construction cost | +57.71% | EGP 220.79 million instead of 140 |
| Exit multiple | −82.01% | 0.72 times EBITDA instead of 4 |
This reorders the questions you take to the market. That the project can absorb a 49.6% rise in the exchange rate at purchase is good news, but it is also a risk you can close completely by securing the currency and paying for the equipment before construction starts. Remember too that this figure measures only the purchase-time rate, in pounds. If you measure your return in dollars, every year the pound weakens reduces the dollar value of your cash flows and of the exit: with all other assumptions unchanged, the dollar IRR falls to 25.23% if the dollar rate rises 5% a year and to 19.54% if it rises 10% a year, against 31.49% in pounds. The full method is in the exchange rate guide linked above. The 10.68% margin on price or occupancy is narrow, and no financial decision closes it; only market evidence does: advance contracts with customers, competitors' rates and occupancy, written demand from exporters.
The exit multiple looks safe, since it would have to fall 82% to erase NPV, but that is misleading for one reason. If you find no buyer, or decide to keep the business without a valuation, NPV without any exit value (recovering only working capital) is minus EGP 16.12 million and IRR is 24.43%, below the discount rate. The project depends on a buyer being there in year eight.
Three scenarios and the effect of delay
One-variable analysis assumes everything else stays put, which is rarely true. A market that squeezes your price usually squeezes your occupancy too, and a period of pound weakness tends to bring higher energy and input costs with it. So we built three scenarios:
- Pessimistic: price 5% lower, occupancy 10% lower, electricity 20% higher, exchange rate at purchase 20% higher (EGP 65.16 per dollar), local construction 15% higher (EGP 161 million), and an exit multiple of 3 instead of 4.
- Base: as in the inputs.
- Optimistic: price 5% higher, occupancy 5% higher (84% once stabilised), electricity 5% lower, and an exit multiple of 4.5.
| Scenario | NPV (EGP million) | IRR |
|---|---|---|
| Optimistic | 166.81 | 37.56% |
| Base | 73.47 | 31.49% |
| Pessimistic | −127.57 | 16.02% |
| One-year delay in opening (other assumptions at base) | 6.80 | 26.43% |
| Pessimistic with a one-year delay | −176.72 | 13.92% |
In the delay case we assumed the investment is paid on schedule; all operations and the exit shift by one year; prices and costs keep rising during the lost year, so operations open at year-two prices and costs; and the project carries half of year one's fixed costs (EGP 16 million) for rent, management and insurance during the delay, carried forward as a tax loss. That single year takes NPV from 73.47 to 6.80, wiping out about 91% of it, because every cash flow and the exit value are discounted for an extra year at 26%, more than the 10% to 12% by which prices and costs rise in that year. If your prices are fixed in contracts that do not escalate during the delay, the damage is worse. Delay, which most studies leave out, is often the most dangerous variable that is never written down.
By the European Commission's yardstick, the project is not low-risk, because NPV does not stay positive in the pessimistic scenario2. Note too that IRR in the pessimistic scenario is still 16.02%. That might look acceptable to someone comparing it with returns outside Egypt, but it is below the CBE's current 20% overnight deposit rate8. That rate may not hold for eight years, but the lesson stands: a pound return should be judged against what pound instruments pay over the same horizon. Comparing with returns in your own currency means converting the cash flows, as our exchange rate guide explains.
Probabilistic analysis: how an acceptable base case can still fall short
The project sits close to the cut-off, exactly the situation in which the ADB recommends a quantitative risk analysis4. We gave six variables triangular distributions, each defined by three values (minimum, most likely, maximum) relative to the base case:
- Storage price: −15% to +5%, most likely at base.
- Occupancy: −20% to +5%.
- Electricity: −5% to +35%.
- Exchange rate at purchase: −5% to +30%.
- Local construction cost: −5% to +30%.
- Exit multiple: 3 to 4.5, most likely 4.
The ranges are deliberately lopsided. Prices and occupancy can surprise you on the downside more than on the upside; costs and the exchange rate can surprise you on the upside more. This is not a personal view: construction cost escalation is documented internationally5, and the exchange rate jump of March 20241 and the commercial electricity increase of April 20267 are local examples of shocks that came in one direction. Even so, the ranges themselves are illustrative assumptions; build yours from the experience of comparable projects, as the European guide recommends.
After 20,000 simulations:
- Probability of a negative NPV, meaning the project fails to earn the required 26%: about 68% (68.33% in this run).
- Mean NPV: minus EGP 27.40 million; median minus EGP 25.32 million.
- In the worst 10% of cases NPV is below minus EGP 94.73 million; in the best 10% it is above only EGP 37.93 million.
- Median IRR is 24.10%, and in the worst 10% of cases it is below 18.51%. No draw produced a negative IRR in nominal pounds, though real returns after inflation are much lower, and 17.32% of draws came in below 20%.
A negative NPV here does not mean losing capital; it means earning less than the 26% you asked for. So how can the base case clear that bar while the project falls short in more than two-thirds of cases? Because the base case uses the most likely value of each variable, and in a skewed distribution the most likely value is not the average. In our distributions the average storage price is about 3.3% below base, average occupancy about 5% below, average electricity, exchange rate and construction cost are all above base, and the average exit multiple is 3.83 rather than 4. Each gap is small, but they all point the same way, and as we saw the NPV is thin. This is the main payoff of probabilistic analysis: it shows that a study slightly optimistic on every line is very optimistic in total.
One limitation: we assumed the six variables are independent. In practice some move together, for example the exchange rate and local construction costs that include imported materials. Positive correlation between downside risks makes the bad tail heavier than this simulation shows.
From results to a decision, and into your own study
Sensitivity analysis does not hand you a ready yes or no. It hands you a list of what has to change for the answer to be yes. In our example, the honest verdict on the study as it stands is: do not invest on these terms. But the analysis shows what to negotiate or verify:
- Early-year occupancy: do not rely on an estimate. Ask anchor customers for letters of intent or advance contracts covering part of the capacity before construction starts, even at a discount. Then recalculate, because the discount itself lands on the most dangerous variable.
- Delay and construction overruns: a fixed-price, fixed-date construction contract with delay penalties shifts part of the risk to the contractor in exchange for a somewhat higher price. Phasing capacity (building half first) reduces the capital at risk.
- Exchange rate at purchase: this risk can be closed by securing the currency and paying for the equipment early, so do not let the 49.6% margin give you false comfort until you know the currency will be available on time.
- Electricity: a clause in customer contracts linking part of the price to energy costs, or rooftop solar, each tested in the same way.
- Exit value: ask whether the project passes if you hold it. If not, you are betting on a future deal market, not on a cold-storage warehouse.
After each change, recalculate everything: base case, tornado table, switching values and scenarios. A change that improves one variable can weaken another, as happens when you buy guaranteed occupancy with a price discount.
Steps for your own study
- Build the base case on annual cash flows, with the exit value on a separate line.
- List the independent variables: price, volume and ramp-up speed, every large cost line, construction cost, construction time, the exchange rate, the discount rate and the exit value.
- Apply the 1% test to rank them, then the ±10% test, and calculate a switching value for each critical variable in its natural unit (pounds, occupancy, months of delay).
- Build pessimistic, base and optimistic scenarios from events that actually happened in the market, and add a delay scenario.
- If the project is large or close to the cut-off, run a simulation with simple triangular distributions.
- Finish with a three-column table: the variable, what you will verify before paying, and the indicator you will track after opening.
If you are investing from abroad, read this alongside our feasibility study guide for foreign investors in Egypt, which covers the rest of the study from your point of view. Execution after the decision, such as company formation, licences and tax, is work for a specialist adviser such as Maher Consulting Firm (mahercf.com).
Common mistakes in sensitivity analysis
- Testing linked variables as if independent: revenue and price, or equipment cost in pounds and the exchange rate. It double-counts the effect and distorts the ranking2.
- One flat percentage with no thought for likelihood: a 10% move in the pound over a project's life is common; a 10% rise in a security guard's wage is not where the risk lies. Give each variable a range drawn from its history and its market.
- Forgetting delay: most studies test prices and costs and forget time, even though one year's delay in our example (NPV EGP 6.80 million) does more damage than a 30% rise in electricity (EGP 17.18 million).
- Testing profit instead of cash flow: accounting profit ignores the timing of investment and working capital. Test NPV and cash flow, and check each scenario's effect on the deepest cash need, as in our break-even and working capital guide.
- Hiding the exit value's weight: always show NPV with and without exit value so the reader knows which assumption the project rests on.
- A polite pessimistic scenario: if the project still makes good money in the pessimistic case, ask whether it is pessimistic at all. Compare it with events that actually happened, such as the March 2024 jump.
- A report with no decision: a neat tornado chart that does not say what you will verify or negotiate is wasted effort. Every critical variable should produce an action.
How Kleverz helps
Kleverz is an AI-powered platform for analysing the feasibility of projects in Egypt. You can start with the free idea check: it takes about 5 minutes and gives you a verdict (proceed, adjust, validate first or avoid), a Kleverz Score out of 100 across five dimensions, the top 3 risks, and a first step for the next 48 hours.
If you decide to go further, the detailed study is built on the numbers you enter: price, direct cost, expected volume, team, city and capital. It covers start-up costs and fixed monthly costs including the employer's social-insurance share; a month-by-month cash flow for the first 12 months and a yearly summary over three years; monthly break-even revenue and the units needed; the operating break-even month, the payback month, the deepest cash need and a recommended capital that adds a two-month reserve; optimistic, realistic and pessimistic scenarios; and the main risks, indicators to track and a week-by-week plan for the first month. It is delivered within 24 hours of payment confirmation, in Arabic or English. The study's three scenarios are the starting point; switching values, delay, exit value and simulation are steps you apply to its results as described here. If your project is in storage or transport, see the logistics company feasibility page.
Frequently asked questions
What is the difference between sensitivity analysis and scenario analysis?
Sensitivity analysis changes one variable at a time, holding the rest constant, to find which variables have the biggest effect on NPV. Scenario analysis changes several variables together to describe a whole state of the market, such as a pessimistic case combining a lower price, higher costs and a delay. The first ranks the risks, the second measures their combined effect, and a good study needs both.
What is a critical variable in a feasibility study?
Under the European Commission's cost-benefit analysis guide, a critical variable is one where a 1% change from its base-case value changes NPV by more than 1%. When NPV is small relative to the investment, most variables can turn out critical, and then their ranking matters more than the label.
What is a switching value and how do I calculate it?
It is the value at which NPV becomes zero when one variable changes and the rest stay fixed. In a spreadsheet you can find it with Goal Seek or by trial: move the variable until NPV reaches zero. In our illustrative example, the switching value for the storage price was EGP 1,027 per pallet per month against EGP 1,150 in the base case.
How far should I move each variable?
Plus or minus 10% is common for ranking variables, but it is not enough to judge risk. Give each variable a range drawn from its history: Egypt's exchange rate jumped in a single day in March 2024, commercial electricity prices were raised by an average of about 20% from April 2026, and international studies show average construction cost overruns of 20% to 45% depending on the type of project.
Do I need a Monte Carlo simulation?
Not always. If NPV stays clearly positive in the pessimistic scenario, scenarios are usually enough. Large projects, or those close to the cut-off, benefit from simulation because it reveals the combined effect of being slightly optimistic on every line. Triangular distributions, with only three values per variable, make it workable in an ordinary spreadsheet.
Sources
- Enterprise. This evening: CBE floats the EGP, goes for 600 bps rate hike (2024-03-06) — secondary source; Daily News Egypt. Egypt floats pound, raises interest rates by 6% to tackle inflation (2024-03-06) — secondary source. Checked 25 November 2026.
- European Commission. Guide to Cost-Benefit Analysis of Investment Projects: Economic appraisal tool for Cohesion Policy 2014-2020 (section 2.9, Risk assessment) — December 2014. Checked 25 November 2026.
- The University of Queensland. Introduction to Financial Management: A Contemporary Approach — 9 NPV: Modelling and Analysis. Checked 25 November 2026.
- Asian Development Bank. Economic Analysis of Projects: Key Questions for Consultants. Checked 25 November 2026.
- Transport Reviews. Flyvbjerg, Skamris Holm and Buhl — How common and how large are cost overruns in transport infrastructure projects? (2003). Checked 25 November 2026.
- Banker. سعر الدولار اليوم الأربعاء 25 نوفمبر 2026 في البنوك (in Arabic) (2026-11-25) — secondary source. Checked 25 November 2026.
- Arab News (Reuters). Egypt raises electricity prices for higher-use households, businesses amid energy crisis (2026-04-05) — secondary source. Checked 25 November 2026.
- Arab News. Egypt's annual urban inflation eases to 12.7% in October (2026-11-10) — secondary source. Checked 25 November 2026.
- PwC Worldwide Tax Summaries. Egypt — Corporate — Taxes on corporate income (2026-08-17) — secondary source. Checked 25 November 2026.